Mill Valley Middle School Modernization Weekly Report – August 14, 2026

Mill Valley Middle School Modernization Phase: Interim Campus Construction August 14, 2026  Work Completed August 8 – 14  ā— Excavated trenches; installed sewer, storm drain, and domestic water utilities; and backfilled trenches with  clean material.   ā— Continued grading the site to prepare the area for interim campus construction.  ā— Placed lightweight fill concrete to cap…